Phase II gets green light, new $2.2M estimate-Rutherford believe costs can be reduced even more
McMinnville officials have agreed to move forward with phase II of the Downtown Economic Revitalization Project. Estimated project costs are currently $2.2 million, and could be reduced even more.
A preliminary estimate made by engineer James C. Hailey has been set at $2.2 million ‘ far less than EG&G’s estimate of $4.2 million.
However, city administrator David Rutherford has been trying to get the cost down even further.
‘I’m trying to see what we can do for $1.5 million and keep you from going into debt,’ said Rutherford.
The city currently has a $1.2 million grant received from TDOT for phase II. Adding the grant match required by the city, $250,000, and that total is almost $1.5 million.
If the project cost can be reduced further, the city wouldn’t have to pay much out-of-pocket expenses. Despite current cost estimates, Rutherford believes he can get the cost down to $1.6 million.
He has been looking at city departments doing more of the work, mostly demolition. Also, Public Works director Bill Brock has been talking to the utility companies and they have agreed to put their utilities underground for the entire project.
Although most of the work will be invasive, some of it will not be. The city has about 400 feet of sewer from Sparta Street almost up to Spring Street, a dead-end line, that needs to be replaced.
For sewer-line replacement, the road will have to be ripped up. However, project construction still includes leaving one lane of Morford Street open at all times.
The new cost estimate also includes adding new areas to phase II. Where construction originally stopped at the intersection of Chancery and Morford streets, this estimate includes work done up to High Street.
This section was added because of the underground utilities. High Street would be a good stopping place, officials have said.
As well as putting utilities underground, replacing sewer lines and addressing the drainage problem, current project plans include installing regular sidewalks and using light poles and traffic signal poles to match the historic look of the ones on Main Street.
Excluded would be stamped concrete and crosswalks. While some residents have complained about the stamped concrete providing a rough ride when driving over it, Mayor Royce Davenport likes this feature. He says if stamped concrete work is not included in phase II, he won’t support the project.
‘If we don’t do that, I’ll vote no,’ said Davenport. ‘If you drive down Main Street, that is what stands out. That’s what gives the design. If we don’t do that, we are wasting our time and our money.’
Discussion was made to adding crosswalks at Spring Street, the post office and College Street. The crosswalks could increase the cost by more than $100,000.
Once officials decide on what work will be done, a timeline for construction, beginning and ending, can be established.