Loud drilling to begin at Civic Center

Residents around McMinnville Civic Center expecting to have a peaceful relaxing day after the hustle and bustle of Christmas might have that peace interrupted to some degree.

Today marks the beginning of geothermal for the Civic Center. Up first will be the noisy drilling of holes in the City ball field.

Mid State Construction, the company contracted by the city to handle the outside geothermal installation at a cost of $348,092, will have two drilling rigs working at the site. The equipment was moved in last Thursday.

According to McMinnville Civic Center maintenance supervisor Mark Kell, the company averages 300 feet per day and each hole needs to be 275 feet deep. Altogether, 56 holes are required for the project.

‘They plan on working until dark every day,’ said Kell. ‘The plan is to begin drilling the day after Christmas and get the holes finished as fast as possible. The only thing that might slow them down is heavy rain.’

As for the noise, there isn’t much the company or the city can do to prevent it. However, those in close proximity are encouraged to keep their windows shut.

The site was chosen after a test hole was drilled in February which showed the site was a good one for geothermal installation. After drilling down 70 feet of dirt, the drill hit coal and water for 30 feet and the rest was solid rock.

After drilling the hole, one of the geothermal loops was placed inside the hold and held by mortar and filled with water. The water was then circulated and tested by a machine to measure how quickly the earth would absorb the heat and also how quickly the earth could heat it back up. The test was promising for a good heating and cooling system.

While Mid State Construction handles the outside work, CHC Mechanical will be working on the inside mechanical at a cost of $873,000. The inside work is expected to cause minimal disruption of activities. To ensure this, the company will be given a list of Civic Center events as well as working closely with Civic Center employees.

System installation is estimated to be right at $1.2 million and completion is expected in the summer of 2008. To pay for the system, an annual payment of $120,000 will be made for the next 12 years.