Motlow College expansion to begin in next 30 days – Addition will more than double size of facility
Cookeville-based Midstate Construction Company was awarded the project last week with a bid of $3 million. The state legislature has appropriated $3.94 million for construction and furnishing expenses.
Built in 1990-91 at a cost of $946,000, the local Motlow campus improvement budget is four times the amount it took to build the school. The expansion is expected to be complete in time for the fall 2008 semester.
The current Motlow facility is 17,000 square feet. The expansion will add roughly another 20,000 square feet.
The addition will be built onto the front of the school. It will include four high-tech classrooms, a science lab, nursing lab and computer lab, a library, and administrative and faculty space. Two of the classrooms will be connected by a partition which can be moved to create a large gathering room.
The new space will enable the college to expand existing programs and also seek new programs to broaden local opportunities for education and job training. Motlow College has enjoyed rising enrollment in recent years and had around 700 students at the end of its spring semester.
‘The expansion is going to be a big asset to the community,’ said state Sen. Jerry Cooper, a longtime Motlow College supporter.
In addition to the expansion, Cooper said he would like to see other changes to the area. Specifically, Cooper would like to see the nearby water tower, which is no longer in use, and the driver’s testing center moved.
‘I’d like to make it so when you look at Motlow College, you don’t see an old water tank and a driver’s testing center,’ said Cooper. ‘I’d like it to look like a building of higher education.’
Cooper said the $3.94 million expansion budget includes roughly $700,000 for a first-rate entrance.
Even though the water tower is no longer in use, it is still in working condition. Cooper indicated it’s possible to give the tank to another community, provided that community pays to remove it. His plans for the driver’s center would be to move it to a different location.
‘The positive enrollment trends at the McMinnville Center, along with the current economic conditions of the area, make the building expansion a most worthy investment by the state of Tennessee for the future of Warren County,’ said Motlow president MaryLou Apple.