City waiting to see if Hailey gains approval from TDOT

Signing with James C. Hailey for phase II of McMinnville?s downtown economic revitalization project is still a wait-and-see situation. The wait could net the city $243,750 in additional grant funds ? or cost the city $600,000.

Elected officials gave Mayor Royce Davenport the go-ahead to sign with Hailey?s company in January. At that time, signing the contract was placed on hold because of the Tennessee Department of Transportation.

When the city received the contract from TDOT regarding a $975,000 grant, which will pay 80 percent of the $1.21 million engineering costs, officials noticed something very interesting regarding the remaining 20 percent requirement the city must contribute.

If the city uses a TDOT-approved engineering service, they could get an additional $243,750 added to the grant, which would pay the full price of engineering costs.

However, Hailey?s company is not on the list of approved engineering services. When the estimated project cost is $4.2 million, every dollar counts especially when those dollars could add up to $243,750.

The process of approval is a matter of filling out the proper paperwork and submitting it to TDOT. At that point, it?s a matter of waiting.

A pressing problem in regards to how long the city can wait is the ARC grant of $600,000. The deadline for that grant is in October. After missing the last grant cycle deadline, the city needs to hire a contractor to apply for this grant before the next deadline.

According to TDOT?s Web site, Hailey?s company is still not on the list of pre-qualified contractors. The list was updated Wednesday.