Now is the time for sewer in Newtown
Is there ever a good time for sewer? If there ever was, now would be that time.
McMinnville?s Water and Wastewater Committee is looking into running city sewer to the Newtown and Pike Hill areas and discounting the cost to connect.
When it comes to the Newtown area, recent construction by the Tennessee Department of Transportation (TDOT) makes this the best time for the city to move on getting sewer as far out as possible.
?If we are going to run sewer out to this area, we need to do it,? said Water and Wastewater director Carl Davis. ?The state wants it done quick and everyone out of the way before paving begins.?
Paving is why now is the right time. If the city can run the lines out to the area before paving begins, the city will save thousands. TDOT will be paying to fix the area anyway, so now is the perfect time.
The estimated cost for the sewer line through Newtown will be $49,180. This cost does not include labor, as the Water and Wastewater Department will be handling the installation. If that department does not do the installation, the cost would be $124,000.
Installed in the Newtown area will be a low-pressure force main. Land owners will not be required to pay any fees unless they want to connect. If a connection is desired, pumps are generally less an $2,000. There?s a connection fee of $400 to $500, and a tap fee of $750.
Given that it will cost less for the city to make the connections as they go, elected officials are looking into offering a tap fee discount for those who wish to connect as the line is being placed. For this discount, people will have to pay beforehand.
Given the urgency of the Newtown expansion, the Water and Wastewater Committee voted unanimously to allow the expansion to begin.
As for the Pike Hill area, elected officials are looking into a sewer forced main verses a gravity flow extension.
? Forced main: If the city goes with forced main, only those who wish to be hooked up to the system will have to pay by purchasing a pump, installation and paying a tap fee. The line is put in with a trencher and takes one week.
This option seems to be the way most cities are going given the cost and ease of installation. Extension with a forced main will cost $4,276.
? Gravity flow: If the city goes with gravity flow everyone will have to pay a sewer fee whether they connect or not. Connection still requires a tap fee. It is put in with a backhoe, requires manholes, is gravity fed and must have connections. The expansion would take two weeks or longer.
Given the difficulty with installation and the expense to taxpayers, cities are moving away from gravity flows. A gravity flow extension will cost $14,710.
Regardless of which is chosen, officials will be giving the tap fee discount to those who want to connect in either area.
Currently, there is no set amount to be discounted. Davis will be estimating the costs and making recommendations during the next Water and Wastewater Committee meeting. During that meeting, officials will make their decision on which sewer extension to use in the Pike Hill area.