Main Street project costs $5.17M: City pays nearly 70 percent
The final cost for the first phase of the Main Street revitalization project is $5.17 million, with the city of McMinnville paying nearly 70 percent of that amount, according to documents released by the city Wednesday.
Project costs were estimated at $4.8 million in the planning stages.
?We were certainly within the range we were shooting for,? said McMinnville Mayor Royce Davenport. ?According to some of the contractors I?ve talked to, it?s not unusual for a project like this to go over 10 to 20 percent.?
The city?s portion of the $5.17 million project comes to $3.56 million. That number does not include the cost of in-house labor involving city employees, as departments did not keep track of the work hours they spent on Main Street. It also does not include the cost incurred by utilities like McMinnville Electric System, which performed in-kind work for the city.
The general contractor, Apex Construction, and the project engineer, EG&G, received the bulk of the final bill.
According to the final contract approved Tuesday by the Board of Mayor and Aldermen, those two companies received $4.0 million.
During the course of the project, items were taken out to reduce construction costs by $45,126. However, other items were added to increase costs by $56,548, leaving the final cost $11,422 higher than the original construction estimate. The changes were due to recommendations by the engineer that were approved by the city.
One major cost-saving area that was removed from the project was The Hole. One area that added significant cost was paving work around the courthouse.
Initially, plans called for shaving down, or milling, the asphalt around the courthouse and paving over the top of it. However, the ground underneath the asphalt was determined to be unstable in places which would have led to cracked pavement in a few years.
That?s when the decision was made to completely remove all the asphalt, place rock in the ground where necessary, then pave over a stable foundation.
?Basically the board felt we wanted to do the job right the first time,? said Davenport, ?and that cost a little more money.?
The punch list is not complete and there are still areas that need a little touch-up work. According to Public Works director Bill Brock, that will be left to the contractor to finish once the final figure is paid.
Grants involved with the project include a $600,000 grant from Appalachian Regional Commission and a $719,000 grant from TDOT. Another $14,166 was gained from insurance recovery.
Other funding includes donations: $140,000 from Warren County government, $125,000 from Main Street McMinnville, and $15,000 from Noon Rotary.
Paying for Main Street
Where the funding came from for the $5.17 million Main Street project:
? City of McMinnville $3.56M
? TDOT grant $719,000
? ARC grant $600,000
? Warren Co. government $140,000
? Main St. McMinnville $125,000
? Noon Rotary $15,000
? Insurance recovery $14,166