A site of mass destruction: Crews continue to tear down old outdoor pool

A site of mass destruction: Crews continue to tear down old outdoor pool

City public works crews are progressing on demolition of McMinnville City Pool. The demolition began last week to make way for an estimated $2 million outdoor pool which will take the place of the former pool. (Amy Satterwhite photo)
If the results of excavating the main drain valve that carried water from the city pool into its deep well are any indication, pipes and other hardware not yet visible may be in just as poor shape.

City public works crews demolishing the old city pool since last week uncovered a drain valve so badly worn, bits and pieces of the rusted, cast-iron piping could be chipped away with finger-tip pressure.

“We were expecting through our reports that the plumbing would be in real bad shape, so it’s confirmed now that we’ve pulled some it,” Public Works Director Bill Brock said of the uncovered drain valve, which is about 6 inches in diameter. Brock said he expects three other drain pipes located under the deep section of the pool to be in poor condition as well.

Workers expect to uncover those pipes next week. Their condition has only been speculation because they are hidden.

“When we get those dug out, by all records, those are going to be in bad shape – real rotten,” Brock said. “There is where I think our major loss was on the pool and there was no way of getting to them until you just destroy everything.”

The drain and underlying pipes were two points of contention about just how badly pool repairs were needed after city officials proposed building an estimated $3.5 million indoor/outdoor aquatic center.

Borrowing money for that proposal was defeated by referendum Jan. 24. After officials announced the city pool would be closed this summer, they formally announced a desire for a new outdoor pool and passed an alternative form of funding April 15.

The new outdoor pool is expected to cost about $2 million and is the same outdoor pool proposed initially, with water play features, new slides, proper depth for diving, competitive swimming lanes and a zero depth, or beach-like, entrance. It will be paid for with capital outlay notes spanning 12 years – about half the time the bond issue voted down in January would have spanned.

City Administrator Herb Llewellyn responded to questions about the condition of the drain valve in earnest.

“I want people to understand we’re going to be honest. There are people who are going to believe that pool was wonderful no matter what,” Llewellyn said. “But I want to do everything we can so they understand it wasn’t because we wanted to build a new pool so we could put our names on it. That was not the motivator.

“The motivator was that we had a pool that was worn out. And the more we can do, the better I like it.”

City workers said Monday they are waiting to see the exact shape of the underlying pipes, which some officials previously thought could have been the source of water leaks estimated as high as 15,000 gallons per day.

In another discovery, workers found the pool walls were created using concrete blocks with concrete poured into them, not a strictly poured wall as was expected. Brock said the shell of the pool was basically solid, but said workers noticed some weak spots and cracks and also suspected leaking at the pool’s expansion joints.

One public works employee working on demolition also said an area where the old kiddie pool was located was wet and there was other evidence of leakage around the site.