Rumors of jail costs exaggerated says committee
Amid rumors that change orders for the Warren County Jail project had reached more than six figures, the Jail Oversight Committee reported in its most recent meeting that, even though there were some expensive changes, including $90,000 to fill a sinkhole, there were actually some change orders that saved the county considerable funds – including a change in the brick specifications that reduced costs by $96,000, and a change on access road construction that saved $25,000.
Once all the change orders, both credit and debit, were calculated, the total cost of change orders, as of July 31, is $65,468, an amount committee members feel is within acceptable limits.
“I don’t think the change orders have been any worse than for any other project like this,” said Commissioner Carl Bouldin. “I think we’ve done pretty good.”
According to Medical Construction Group site superintendent Kenneth Bratcher, who was overseeing the setting of bar joists and roof decking last Tuesday, the project is moving along well.
“We’re getting prepared for the roof to go on,” Bratcher said, adding that the roofing contractor should begin work as early as tomorrow. “That’ll be the big thing, because when the roof goes on, then all the inside work starts. Putting the bars and the doors in on the cells, and then from there the painters will start. It’s going along real well.”
The steel sub-contractor, Barnett Steel out of Goodletsville, was using a 130-ton, diesel-powered crane to set the steel.
“The metal deck lays up there and welds down to these joists,” Bratcher explained. Around 3 inches of insulation will then be attached to the decking with screws. “Then after they get that insulation on there, they’ll come back and you’ll have a Firestone rubber roof put on it.”
Though the building will be dried in soon, Bratcher estimates, due to furniture and electronics, it will probably be some time in January before prisoners are actually moved into the jail addition. At that point, renovation of the old jail will begin, which will be a major project in its own right, according to Bratcher.
“We’ve got a set of drawings,” Bratcher said. “We know exactly what we’re going to do. Demolition is the biggest part of that.”
All the electrical, roof, and interior will be razed, Bratcher said, noting about the only thing left that would be usable would be the walls.
“You see the old metal roof out there,” he said. “That will be demolitioned away. Then we’re going to come back and make it look like this building. It’ll have a rubber roof.”
Once renovation is complete on the old section, it will be turned into offices for jail personnel and booking facilities, among other functions.