The Warren County School Board will soon be debating whether to renovate Nunley Stadium or build an entirely new football stadium on the campus of Warren County High School.

“Our stadium’s in bad shape. Anyone who sees it will tell you that. Either way, something has to be done,” county athletic director Andy Jacobs told members of the School Board’s Building, Grounds and Insurance Committee Thursday night.

Talk of renovating the current stadium, or building a new one, had its origins in another committee discussion of crowd control during games at Nunley Stadium. The problem, the committee and Jacobs agreed, was the large number of people who loiter outside the stadium, in the area between the press box and the middle school, during game time.

Jacobs suggested erecting some type of portable fencing which would cordon off the area in question. Later, the suggestion was made that in light of the loitering and many other problems, such as deteriorating concrete and faulty bathrooms, perhaps it would be in the school system’s best interest to build a new stadium at the high school. Soon after, Athletic Committee Chairman Edd Cantrell directed Jacobs to come up with cost projections for the renovation of Nunley Stadium and a new stadium.

To bring Nunley Stadium up to par, Jacobs told the committee, would cost in the neighborhood of $898,000. The biggest portion of this estimate is $465,000 to put in new bleachers on the home side and $175,000 for bleachers on the visitor’s side. Home and visitor’s side restroom and concessions renovations are estimated to cost a combined $128,000. The remaining renovation estimates include $40,000 for fences and ticket booths, $60,000 for the press box and $30,000 for other items.

The estimated cost to build a utilitarian new stadium, Jacobs said, will be around $565,000. This estimate includes $400,000 for bleachers and a press box, $18,000 to 20,000 for fencing, $60,000 to 80,000 for lighting, $50,000 for restrooms and concessions and $15,000 for field renovations.

An additional $45,000 to 80,000 would be necessary for a track. A fieldhouse would run $300,000. If all features were to be included, Jacobs estimated the cost of a new stadium at $925,000.

Director of Schools Dr. Jerry Hale told committee members in years past, the school system might have been able to take on a project such as renovation or building a stadium, as it has done with the building additions at the five outlying schools. But given the current economic outlook, either option would be difficult to do without asking for financial assistance from the Warren County Commission.

Hale added if the board opts to build a new stadium it could always do so in phases over several years. School Board Chairman Mike Holland reminded committee members that even if the board were to build a new stadium, it would still have to make some renovations and repairs to Nunley Stadium as the middle school would still play its games there.

No decision was made other than to put the item on the agenda for the School Board’s annual retreat, usually held in February.