Work begins on Centertown school
|
Although the official groundbreaking ceremony was held in January, due to weather conditions major work by Mid State Construction didn?t start until last week.
Architect Derrick Clemow of Upland Design Group said early construction will consist mainly of setting up what is called a detention area for storm drainage, which is required by the state, and working out the routing of utilities. Charlie Turner Road also received some attention.
?The reason we?re talking about Charlie Turner Road is it?s a secondary means of access,? Clemow said, noting the road, which runs along the east side of the school property, could also be a utilized to bring in utilities like power and water.
Eventually, plans are to widen and improve Charlie Turner Road, but for now, Clemow says construction will begin by connecting the site to Highway 70.
?We?re starting construction at the other end,? Clemow said. ?For now all we?re doing is building a road to connect the site to Highway 70.?
Once that road is built, construction crews will start clearing for pavement and actual construction of the building will follow soon after, within two weeks or so.
?A lot of progress has been made,? said Clemow, noting that even though the site may not show any signs of major construction yet, a lot of work has been done as far as laying out the engineering site plans for the school. Clemow and school system maintenance director Donnie Caldwell say there will eventually be progress reports posted on the Internet so those interested can keep track of construction.
?We?re going to post progress photos on the school Web site,? Clemow said.
Caldwell said it will take some time to set up a system to post the reports, but it will eventually be available for public access as construction proceeds.