Funding questions cloud Woodbury 4-lane project-Federal funds rescinded
Local officials concerned about continued funding for the four-lane to Woodbury can join a growing list of Tennesseans worried about road projects.
The Tennessee Department of Transportation announced last week it won’t receive around $66 million in funding it had already been promised from the federal government. Combined with previous cutbacks, the federal government has rescinded over $237 million in road funding to Tennessee since December 2005.
‘That’s money we’re not going to get back,’ said TDOT spokeswoman Jennifer Osborne-Flynn. ‘The federal government is rescinding money and the price of fuel, the price of construction, and the price of equipment is skyrocketing.’
The good news is the federal cuts will not impact the 1.1-mile phase of the Woodbury four-lane that’s currently under construction. It widens Nashville Highway all the way through Newtown to Spring Valley Road. Funding for that portion has already been received, although it’s only a short segment of the overall project.
As for the rest of the project, about 13 miles from Spring Valley Road to Billy West Road in Cannon County, the lack of federal funding could delay construction.
‘We will not stop the project,’ said Osborne-Flynn. ‘Projects under development will continue. But due to the rescissions, some portions of the project may be delayed.’
The next phase of the four-lane, from Spring Valley Road to Highway 287 in Centertown, is currently in TDOT’s three-year plan.
Money has been appropriated to purchase right of ways, according to Osborne-Flynn, but no funding has been earmarked for construction costs.
If the federal government continues to cut highway funding, it will have an impact, according to TDOT Commissioner Gerald Nicely.
‘Nearly 50 percent of the department’s budget comes from the federal government, so a reduction in these revenues significantly impacts the resources available to TDOT,’ said Nicely. ‘This loss of funds, coupled with the massive inflation in the cost of construction materials, further reduces our ability to address the transportation needs of the state.’
TDOT gets most of its other funding from the state’s tax on gasoline, which has not increased since 1989. Tennessee’s tax of 20 cents a gallon on gas is divided four ways, with TDOT getting 12 cents of it, or 60 percent.
The remaining state tax money goes to the county (25 percent), the city (13 percent), and the state’s general fund (2 percent).
State Rep. Charlie Curtiss says the federal cuts are creating problems but he doesn’t see anything that will endanger the rest of the four-lane project from reaching completion.
‘It could slow the project down, but it’s not going to stop it,’ said Curtiss. ‘We’re going forward with the projects that have been approved.’
Osborne-Flynn said the projects that will be impacted the most are the ones which haven’t been started.
‘Instead of starting new projects, we’re going to finish the ones we have,’ she said.
The rescission of funds affects all states, not just Tennessee. A rescission of funds means that federal dollars promised to the state have been canceled and will not be received.
Four-lane shortened
The four-lane to Woodbury is no longer projected to extend all the way to Woodbury. Seven miles have been removed from what was once a 21.1-mile project.
According to TDOT spokeswoman Jennifer Osborne-Flynn, seven miles of Nashville Highway, from Woodbury to Billy West Road, will no longer be funded in the project.
Current construction in Newtown is scheduled to be finished in June. Construction for the next phase, from Spring Valley Road to Highway 287 in Centertown, is scheduled to begin in fiscal year 2010.