Water project now fully funded

The final $500,000 needed to fully fund the $3.7 million project to pump water atop Harrison Ferry mountain has been approved by Gov. Phil Bredesen and Economic and Community Development Commissioner Matt Kisber.

With all of the needed funds in hand, it’s possible for work to begin in about 90 days. From there, the project is expected to take around two years to complete.

In approving the grant Bredesen said he was gratified the state was able to help fund improvements to the county’s infrastructure.

‘I’m very pleased the state of Tennessee can offer this financial assistance to Warren County for its water system improvement project,’ Bredesen said. ‘The types of infrastructure repair and modernization projects funded by community development block grants benefit and boost development at the local level and lead to the continued improvement of our state’s economic health.’

State Sen. Jerry Cooper, who was instrumental in obtaining the various grants, along with the other regional officials, noted securing funding for the project was very much a team effort.

The project will use 12-inch pipe to run water from Warren County Utility District up the mountain. It will be stored in a water tower atop the mountain.

‘This is the fruits of a concerted effort toward development in Warren County and is truly encouraging,’ Cooper said. ‘This CDBG grant represents a significant step of progress in the economic potential of our community.’

Cooper said this was one of the projects he wanted to see completed before he left office because of its importance to the region.

‘I’m really excited about this,’ Cooper said. ‘Because of the impact this is going to have on so many people in Warren County and adjacent counties. We like to be able to help people in need and this is one of those projects that’s going to help a lot of people. This is going to make my Christmas.’

State Rep. Charles Curtiss said other rural counties should concentrate on water projects like this in the coming years.

‘We’re worried about things like broadband cable access and there are people out there who don’t even have water,’ said Curtiss.

Warren County Utility District general manager Mike Green said the utility, which is assuming a loan to fund $1 million of the project, is eager to begin construction.

‘We’re hoping to get the project going within maybe 120 days or so,’ Green said. ‘The engineer, James C. Hailey, has explained to me that once we get everything settled in it’ll take him about 90 to 120 days to get this project bid. So by spring or mid-summer we should be trenching.’

Green estimated it would take around two years from start to finish to complete the project.

The grant was approved following an application by Warren County and has the support of County Executive John Pelham, Cooper, Curtiss, and state Rep. Judd Matheny. U.S. Sens. Lamar Alexander and Bob Corker, and Congressman Lincoln Davis, aided in securing the funds.

‘Our communities deserve congratulations for working together to secure this grant,’ Curtiss said. ‘Community development is impossible without teamwork, and this award is evidence that Warren County understands that need for cooperation.’

Pelham, who has worked tirelessly to promote this project, even making a trip to Washington, D.C. to solicit aid at the federal level, said he is thrilled to see the project fully funded. Pelham says the cooperation between communities and regional officials, as well as government entities like the Upper Cumberland Development District, that went into the more than year-long process is unprecedented.

‘So many people have worked so hard on this,’ Pelham said. ‘It would be my desire to give credit to every single individual that has labored and spent so much time to make this become a reality today. And certainly, I have to thank Sen. Cooper, Rep. Curtiss, Rep. Judd Matheny, Rep. Bill Harmon, the county mayors in surrounding counties, the list just goes on and on of the people that played a role in this.

‘This project is vitally important to our citizens, and for me, in my heart, to know that we’re going to be able to take care of the citizens of Warren County on Harrison Ferry and help in surrounding counties,’ Pelham said. ‘Well, that’s what this job is all about, providing for their needs. It doesn’t get any better than that.’

Commissioner Kisber noted CDBG grants play a major role in improving infrastructure statewide.

‘CDBG grants offer needed support to communities at the most basic levels of infrastructure, including well-kept roads and effective water and sewer facilities,’ Kisber said. ‘ECD is pleased to lend its support to this program that is so essential to the progress of communities across the state.’

Where the funding is coming from:

‘ $1.5 million ‘ state appropriation

‘ $500,000 ‘ CDBG grant

‘ $1 million ‘ Warren County Utility District loan

‘ $700,000 ‘ USDA Rural Development grant