Two roads planned for industrial park
After more than a year of preparation by county officials and the Industrial Development Board, Mountain View Industrial Park will benefit from two major road projects designed to make available land at the facility more accessible to potential industry and businesses.
The projects include a short access road, located across from Morrison Tool & Fab, that will open up approximately 60 acres of land which was previously inaccessible. Also included is a connector road that will run from the current three-lane road by Yorozu across the back side of the industrial park to Doyle Frazier Road.
The access road has already been bid out and is currently under construction. This project, with a cost of approximately $100,000, is being financed by the Industrial Development Board, utilizing funds it receives from the county and city each year.
The paved connector road represents a significantly larger project at $2.5 million, with 85 percent being financed by Congressional earmark money in the form of a matching grant.
‘This is the result of the work of Congressman Lincoln Davis,’ said County Executive John Pelham. ‘We really appreciate his help in getting us this federal money.’
The federal money will come to around $2 million, according to Pelham, with the balance coming from the county. Pelham says since the county owns the land and will be giving right-of-way approval, the cost of the property used for right of way can be applied as a portion of the in-kind contribution for the county’s matching part of the grant.
This project also required the Industrial Development Board to complete wetland mitigation on an area of the park before it could move forward. This has now been done and Pelham says the county has been working with state officials on how best to proceed.
‘Now that we do have the wetland mitigation complete, we’re ready to move forward,’ said Pelham. ‘We have drafted a letter to TDOT requesting them to manage this project and begin engineering on it as soon as they can.’
Another benefit, according to Pelham, is that dirt that needs to be moved to level an area of county land behind Accu-Router will be used in the construction of the connector road, thus making that land available for construction of a new spec building should the county decide to do so in the future.
‘It’s killing two birds with one stone,’ Pelham said. ‘We’re leveling the area off and essentially building a pad as a proposed location for a spec building later on.’
Pelham says this is important because most of the available industrial buildings in the county have been filled.
‘This year, with all the properties that we have either sold or leased, we have taken the majority of the properties we have in the county off the market,’ Pelham said. ‘So we need a spec building and we have been discussing that. These road projects will certainly do a lot to make our industrial park more attractive to industry.’