Can bridge stay open? – Residents encouraged to ask questions at public meeting
|
The bridge is scheduled to be closed, demolished and rebuilt beginning in 2008 with construction expected to take more than two years. As that time gets closer, public concern grows.
Despite all the concern, apparently the most important invitation to the meeting wasn?t extended. After being contacted by the Southern Standard, TDOT spokesperson Jennifer Osbourne could find no one in that department who received an invitation to the meeting. According to Osbourne, given enough advanced notice, TDOT would have found someone to attend the meeting despite local statements to the contrary.
When asked why TDOT was not invited, Mayor Royce Davenport said this is a public information session, not a hearing. If this had been a hearing regarding the bridge, then TDOT would be there.
?This session is meant to be for public information,? Davenport. ?It is not a hearing and not an argument. All this is for is to answer questions regarding concerns such as fire and ambulance response. We want to get the information to them but TDOT?s plans are drawn.?
Tuesday night?s session will have two parts:
? 6 to 6:30 p.m. ? An open informal session. This session will be the time in which concerned citizens can ask questions regarding the bridge, or any other city procedures or operations, and have their questions answered by an elected official or a city department head.
? 6:30 to 6:45 p.m. ? A formal session. This session will be more structured as people will be seated. Anyone with a question that didn?t get answered in the beginning session can raise their hands and have their question addressed.
At the Standard?s request, Osbourne was able to get a few questions answered by TDOT?s bridge architect. Among the questions answered was whether TDOT would consider building a new bridge to the left or right of the current bridge to allow the current bridge to remain open during construction.
According to Osbourne, alignment shifts are probably out of the question. Any changes in alignment would require the department to restart the environmental process and have significant impact on Riverfront Park and area property owners.
If the plans could be changed allowing the bridge to remain, the city, or some other governmental entity, would have to accept ownership and liability for it. No maintenance funds would be forthcoming from state or federal government. Future expenses with this decision could be considerable.
If the controversy continues, TDOT will not abandon or refuse to replace the bridge. The state cannot, and will not, abandon the bridge as it is a vital link in a state route and is necessary for continuity.
Although TDOT says that keeping the bridge from being removed isn?t possible, Westwood businesses are hoping the bridge remains open but are bracing for the worst if it closes.
Westwood Amoco owner Cindy Thomas hopes the bridge closing doesn?t close her business, but she thinks it will.
?We aren?t planning to close as soon as the bridge is closed,? said Thomas. ?But I think it is in our future. We will try to stay open as long as we can but we just don?t think there will be enough support to stay open. I think we will probably end up closed after the bridge does.?
According to Thomas, a lot of her business is in the morning. She says while people are passing through on their way to work, and teens are on their way to the high school, they stop in for a quick breakfast. Once the bridge is closed, she believes most people won?t go out of their way to get breakfast from her store and will instead go somewhere else.
Gordon McGee Jr., vice president of Pioneer Building Supply and one of the owners, has the same concern for his business, as well as the safety of the business, its employees and Westwood residents.
?That is the main entrance into the area and where our main traffic supply comes from,? said McGee. ?Anyone in the downtown area will have to re-route all the way back around the bypass to come visit us or take the Frank G. Clement Bridge and come that way. I?m not sure customers would want to go out of their way to buy from us. We are also concerned with safety. What if someone were to be hurt while on the job or the structure was to catch on fire? The extended time to get emergency services is another major concern I hope the city addresses.?